Cuyahoga County Planning Commission Cuyahoga County Planning Commission
 
 

Home

DOPWIC Program Year 2000 Awards

The tables below show the District One Public Works Integrating Committee (DOPWIC) recommendations for Program Year 2000. Projects are shown by funding category:

SCIP Grant, Loan and Loan Assistance Funds - $15,453,200

COMMUNITY PROJECT AWARD
GRANT LOAN LOAN
ASST
Berea Front Street Water/Sewer Project $299,350    
Brooklyn Biddulph Road Reconstruction $100,000    
Chagrin Falls Bell Street Improvements $148,800    
Cleveland Road/Bridge GO Bonds I     $364,317
Cleveland Road/Bridge GO Bonds II     $754,555
Cleveland Hts. Taylor Road Rehabilitation   $336,500  
East Cleveland Euclid Avenue Rehabilitation $2,000,000 $3,186,729  
Euclid East 222nd Street Watermain   $997,450  
Garfield Heights Broadway Road Reconstruction $742,391    
Lakewood Narragansette/Niagra Reconstruction     $58,375
Lyndhurst Watermain Replacement $111,133    
Maple Heights Industrial Ave/E.141st Street $1,644,803 $1,315,842  
Mayfield Village SOM Ctr/White Road $350,000 $635,504*  
Oakwood South Oak Leaf Road $100,788    
Olmsted Falls Phase III Sanitary Sewer Replacement $1,252,230    
Parma Heights Nelwood Storm Sewer $50,000    
Pepper Pike Fairmount Boulevard Improvement $499,952    
Pepper Pike Gates Mills Blvd. Improvement     $160,716
South Euclid Liberty Road Bridge   $526,590  
University Hts. Intercommunity Sanitary Sewers $682,405 $387,000  
TOTAL $6,729,622 $7,385,615 $1,337,963

* - SCIP loan balance not enough to fund full request. Recommended award is $64,496 short of amount requested. When additional SCIP loan funds become available the funds will be awarded to this project to make up the shortage.

LTIP Funds - $8,192,400

COMMUNITY PROJECT AWARD
Cleveland State Road Reconstruction $4,051,840
Cleveland West 110th Street Reconstruction $1,961,840
Cleveland East 110th Street Reconstruction $2,178,720 *
Moreland Hills Bentleyville Road Slope Stabilization $96,250
Oakwood Village Lamson Road Reconstruction $64,726
TOTAL $8,192,400

* - LTIP balance not enough to fund full request. Recommended award is $181,280 short of amount requested. When additional LTIP funds become available they will be awarded to this project to make up the shortage.

Revolving Loan Program Funds - $1,688,200

COMMUNITY PROJECT AWARD
Lakewood Watermain Replacement Program $1,193,831
Parma Heights Denison Boulevard Reconstruction $400,000
TOTAL $1,593,831

Balance remaining - $94,369.

Contingency Projects

COMMUNITY PROJECT AWARD TYPE
Bedford Oxidation Tower at WWTP $1,890,000 Grant/Loan
Berea Fillier Street Waterline $75,500 Grant
Berea Jacob Street Waterline $55,700 Grant
Solon Aurora West Sewers $2,000,000 Loan
Lakewood Lakewood Heights Boulevard $232,560 Grant
TOTAL $5,570,716

Small Government Recommendations

The following projects, listed in priority order, are being recommended by the District One Small Government Subcommittee for consideration by the Small Government Capital Improvements Commission for small government funding.

The OPWC sets aside $12.5 annually for projects from communities with populations under 5,000. The projects will be evaluated along with other projects from around the state for this funding.

COMMUNITY PROJECT RECOMMENDATION
Walton Hills Barclay Pump Station Project $158,100 GRANT
Walton Hills Dunham Road Watermain Phase I $105,290
$105,290
GRANT
LOAN
Newburgh Heights Brow Avenue Sewer Relief $103,116 GRANT
Oakwood Sanitary Sewer Pump Station $93,760 GRANT
Bentleyville Chagrin River Road Stabilization $350,000 GRANT
Brooklyn Heights Street Reconstruction Program $1,273,950 GRANT
TOTAL $2,350,482

<< 1999 Awards | DOPWIC Home | 2001 Awards >>